A simulation and evaluation of earned value metrics to forecast the project duration

  • Theoretical Paper
  • Published:
Journal of the Operational Research Society

Abstract

In this paper, we extensively review and evaluate earned value (EV)-based methods to forecast the total project duration. EV systems have been set up to deal with the complex task of controlling and adjusting the baseline project schedule during execution, taking into account project scope, timed delivery and total project budget. Although EV systems have been proven to provide reliable estimates for the follow-up of cost performance within our project assumptions, they often fail to predict the total duration of the project. We present an extensive simulation study where we carefully control the level of uncertainty in the project, the influence of the project network structure on the accuracy of the forecasts and the time horizon where the EV-based measures provide accurate and reliable results. We assume a project setting where project activities and precedence relations are known in advance and do not consider fundamentally unforeseeable events and/or unknown interactions among various actions that might cause entirely unexpected effects in different project parts. This is the first study that investigates the potential of a recently developed method, the earned schedule method, which improves the connection between EV metrics and the project duration forecasts.

This is a preview of subscription content, log in via an institution to check access.

Access this article

Price excludes VAT (USA)
Tax calculation will be finalised during checkout.

Instant access to the full article PDF.

Institutional subscriptions

Figure 1
Figure 2
Figure 3
Figure 4
Figure 5
Figure 6
Figure 7
Figure 8

Similar content being viewed by others

References

  • Anbari FT (2003). Earned value project management methods and extensions. Project Mngt J 34: 12–23.

    Google Scholar 

  • Christensen DS (1993). The estimate at completion problem: A review of three studies. Project Mngt J 24: 37–42.

    Google Scholar 

  • Christensen DS, Antolini RC and McKinney JW (1995). A review of EAC research. J Cost Anal Mngt (Spring):41–62.

  • Cioffi DF (2006). Completing projects according to plans: An earned-value improvement index. J Opl Res Soc 57: 290–295.

    Article  Google Scholar 

  • Cooper KG (2003). Your project's real price tag—letters to the editor. Harvard Business Review 81: 122.

    Google Scholar 

  • Covach J, Haydon JJ and Riether RO (1981). A Study to Determine Indicators and Methods to Compute Estimate at Completion (EAC). ManTech International Corporation: Virginia.

    Google Scholar 

  • Demeulemeester E, Vanhoucke M and Herroelen W (2003). RanGen: A random network generator for activity-on-the-node networks. J Scheduling 6: 13–34.

    Article  Google Scholar 

  • Elmaghraby SE and Herroelen W (1980). On the measurement of complexity in activity networks. Eur J Opl Res 5: 223–234.

    Article  Google Scholar 

  • Fleming Q and Koppelman J (2003). What's your project's real price tag?. Harvard Business Review 81: 20–21.

    Google Scholar 

  • Fleming Q and Koppelman J (2005). Earned Value Project Management, 3rd ed. Project Management Institute: Newtowns Square, PA.

    Google Scholar 

  • Henderson K (2003). Earned schedule: A breakthrough extension to earned value theory? A retrospective analysis of real project data. The Measurable News (Summer):13–17, 21–23.

  • Henderson K (2004). Further developments in earned schedule. The Measurable News (Spring):15–16, 20–22.

  • Henderson K (2005). Earned schedule in action. The Measurable News (Spring):23–28, 30.

  • Herroelen W and De Reyck B (1999). Phase transitions in project scheduling. J Opl Res Soc 50: 148–156.

    Article  Google Scholar 

  • Jacob D (2003). Forecasting project schedule completion with earned value metrics. The Measurable News (March): 1, 7–9.

  • Jacob DS and Kane M (2004). Forecasting schedule completion using earned value metrics… revisited. The Measurable News (Summer):1, 11–17.

  • Lipke W (2003a). Schedule is different. The Measurable News (Summer): 31–34.

  • Lipke W (2003b). Deciding to act. Crosstalk 12: 22–24.

    Google Scholar 

  • Lipke W (2004). Connecting earned value to the schedule. The Measurable News (Winter):1, 6–16.

  • Loch CH, DeMeyer A and Pich MT (2006). Managing the Unknown: A New Approach to Managing High Uncertainty and Risk in Project. John Wiley and Sons, Inc.: New Jersey.

    Book  Google Scholar 

  • Patterson JH (1976). Project scheduling: The effects of problem structure on heuristic scheduling. Nal Res Log 23: 95–123.

    Article  Google Scholar 

  • Tavares LV, Ferreira JA and Coelho JS (1999). The risk of delay of a project in terms of the morphology of its network. Eur J Opl Res 119: 510–537.

    Article  Google Scholar 

  • Tavares LV, Ferreira JA and Coelho JS (2002). A comparative morphologic analysis of benchmark sets of project networks. Int J Project Mngt 20: 475–485.

    Article  Google Scholar 

  • Tavares LV, Ferreira JA and Coelho JS (2004). A surrogate indicator of criticality for stochastic networks. Int Transac Opl Res 11: 193–202.

    Article  Google Scholar 

  • Vandevoorde S and Vanhoucke M (2006). A comparison of different project duration forecasting methods using earned value metrics. Int J Project Mngt 24: 289–302.

    Article  Google Scholar 

  • Vanhoucke M, Coelho JS, Tavares LV and Debels D (2004). On the topological structure of a network. Working Paper 04/272, Ghent University.

Download references

Author information

Authors and Affiliations

Authors

Corresponding author

Correspondence to M Vanhoucke.

Rights and permissions

Reprints and permissions

About this article

Cite this article

Vanhoucke, M., Vandevoorde, S. A simulation and evaluation of earned value metrics to forecast the project duration. J Oper Res Soc 58, 1361–1374 (2007). https://doi.org/10.1057/palgrave.jors.2602296

Download citation

  • Received:

  • Accepted:

  • Published:

  • Issue Date:

  • DOI: https://doi.org/10.1057/palgrave.jors.2602296

Keywords

Navigation